Lucknow Building Regulations And Permit Requirements In Detail

Building or altering a home in Lucknow can feel like walking through a maze. Plot sizes, road widths, safety checks—each step has its own form and fee.

Lucknow Building Regulations And Permit Requirements

This guide shows what papers you need, where to submit them, and the special rules that change from Chowk to Shaheed Path. Read it once before you call the mason; it will save you both money and headaches.

What Are The Lucknow Construction Regulations And Permit Requirements?

The Lucknow Development Authority (LDA) and the state housing department control how and where you can build. 

They look at road width, plot size, building height, safety, and even the look of shopfronts in heritage streets. Following the rules saves you from fines, demolition notices, and endless file chasing.

Permit Basics in Five Steps

StepWhat happensWhere to do itAverage time*
1Hire a licenced architect/engineer to draw the plan and create the online file.Any registered professional
2Online application on the “Building Plan Approval System” (BPAS).upobpas.in30 minutes to upload
3Automatic checks for plot size, land-use, set-backs and FAR.BPAS portalInstant
4Departmental vetting (fire, environment, traffic).Handled inside BPAS7–30 days
5Pay fees & download approval letter.BPAS portalSame day after clearance

*For a normal house, the portal now clears many files in one week, far faster than the old paper method.

Key Technical Terms (Kept Simple)

TermPlain meaning
FAR / FSIHow much floor area you may build compared with the land area. Lucknow average is 1.25 – 1.5. 
Set-backOpen space to keep on all sides of the plot.
Purchasable FARExtra FAR you may buy by paying a fee (not for stand-alone houses or factories).
Safety auditA check every 10 years for old high-rise buildings; the owner pays. 

Area-Wise Highlights

(Rules shown here are the ones that most affect ordinary owners. Always cross-check the exact bylaw before spending money.)

Area / zoneSpecial rule setWhat it means for you
Old City core – Chowk, Aminabad, KaiserbaghOld Built-Up Area clauseNo map approval needed if the plot is ≤ 100 m²; standard plan given for plots up to 300 m². Saves time but you must respect set-backs. 
Hazratganj & Andaz-e-Awadh heritage corridorFaçade guidelinesShopfront colour, signboard size, and balcony grills must follow LDA heritage palette; height generally capped at four storeys. 
Gomti Nagar & Gomti Nagar Extension (Shaheed Path)High-growth corridor, Metro Influence ZoneWider roads (≥ 24 m or ≥ 45 m) allow higher FAR, sometimes up to 300 %. Suitable for high-rise flats, offices, malls. 
Indira Nagar & Faizabad Road beltRegular residential layoutMinimum apartment plot size now only 300 m²; typical FAR 1.5. Good for low- and mid-rise apartments. 
Kanpur Road, Transport Nagar, AlambaghMixed use plus safety focusOld towers must pass the 10-year safety audit; new buildings on narrow roads (< 18 m) cannot exceed mid-rise height. 
Peripheral villages (Gosainganj, Mohanlalganj, Sarojini Nagar)Semi-urban rulesAgricultural land first needs land-use change; boundary walls need prior intimation to LDA. 

Practical Tips from Locals

  1. Check road width on site. The rule is measured between compound walls, not from the centre line.
  2. Keep digital copies of every receipt and plan. The BPAS portal lets you download approvals any time for banks and buyers.
  3. Co-ordinate with your neighbour before digging a basement; disputes often delay the completion letter.
  4. Plan for rain-water harvesting early. Adding it later costs double, and the inspector will not issue occupancy without it.
  5. Watch for new bye-law updates. LDA is revising FAR and mixed-use norms in 2025; higher incentives may come for plots along the metro and 45 m expressway. 

Safety, Green, and Comfort Duties

  • Rain-water harvesting: Plots 300 m² and larger must show tanks and pipes in the plan.
  • Fire stairs and pumps: Needed when the building is more than 15 m tall or holds more than 12 flats.
  • Tree planting: Two shade trees on every plot over 300 m²; take a photo when they are planted for your completion file.
  • Disabled access: Ramps, handrails and one toilet on the ground floor for public buildings and flats above 12 units.

Five Common Mistakes and How to Avoid Them

  1. Road width counted from wrong point. Measure wall to wall, not centre line.
  2. Basement under neighbour’s land. Keep excavation inside your plot; take joint photos before digging.
  3. Skipping mutation. Update land records right after purchase—banks and LDA both look at this sheet.
  4. Waiting too long for completion. Apply as soon as plaster and rain-water tank are ready; do not cross five years.
  5. Adding extra floor later. Get a revision plan first; fines for illegal floors are heavy and regularisation is uncertain.

Frequently Asked Questions

How much time does a normal house plan take?

For a simple two-storey house on a regular plot the BPAS site often gives clearance in about seven days once fees are paid.

Do I need a permit for a 70 m² single-floor house in Chowk?

No map is needed under the old-city rule, but you must file a self-declaration and follow side set-backs.

chowk

Can I run a small gym on my ground floor?

A move is under study to allow small commercial use on roads 24 m or wider after paying extra charges. Wait for the final rule before fitting machines.

Who checks if my architect is licensed? 

You can type the person’s registration number on the BPAS portal under “Verify Technical Person” and see if it is active.

Is bore-well approval needed?

Yes. For plots above 500 m² you must get a no-objection letter from the Ground-Water Department before drilling.

What is a compoundable offence?

Tiny errors like a 30 cm projection or a stair tread inside the set-back can be regularised after you pay a set fine. Extra floors, illegal basements or covering set-backs cannot be compounded.

Does Lucknow give any fee rebate for green buildings?

Yes. If you secure an IGBC or GRIHA three-star rating, LDA refunds five per cent of the development charge once the building is complete.

My 12-storey tower is 15 years old. What now?

Under the new safety drive, you must get a structural and fire audit every ten years by a consultant on the LDA panel and submit the report online. Failing to do so brings stiff penalties.

How long can I delay moving in after approval?

Finish and apply for the completion certificate within five years. After that the permit lapses, and you must start the map process again.

Last Word

Lucknow’s rules may look heavy, yet most are aimed at safety, heritage protection and fair use of land. If you start with a registered architect, upload your drawings through BPAS and follow the set-backs and FAR for your area, approvals now arrive in days, not months. Stay alert to updates, keep your papers tidy, and building in the City of Tehzeeb becomes far simpler.